Project Management Test

TestDome skill assessments are used by more than 6,000 companies and 450,000 individual test takers.

Jobseekers: Get a Certificate

Take a Practice Test

Companies: Try First, Pay Later

Sign Up To Use This Test

The Project Management test evaluates a candidate’s ability to initiate, plan, execute, track, monitor, and complete the work of a team to achieve the specific goals of a project.

It's an ideal test for pre-employment screening, for candidates who are expected to manage a project and the work of a team or take ownership of their own workload.

This test requires candidates to answer multiple-choice questions about the principles and core subjects within the project management discipline.

Recommended Job Roles
Project Manager
Sample Candidate Report

Sample Free Questions

Management

1min
  -  
Easy  
  -  
MCQ

Project Planning Project Management Public

How do the best project managers spend the majority of their time?

Poor Connection

2min
  -  
Easy  
  -  
MCQ

Team Communication Project Management Public

A team member calls you mid-flight to inform you about an idea that she had to change one part of the solution design that she is going to present at tomorrow’s customer meeting. She briefly explains her idea to you, but the mobile connection is poor and the call is disturbed with noise and short interruptions. How do you respond?

Active Project

7min
  -  
Easy  
  -  
NUM

Project Risk Management Project Management Public

A company currently has three active projects:

  • Project A has a 85% chance of a 230,000 USD profit and a 15% chance of a 230,000 USD loss.
  • Project B has a 55% chance of a 900,000 USD profit and a 45% chance of a 900,000 USD loss.
  • Project C has a 73% chance of a 300,000 USD profit and a 27% chance of a 250,000 USD loss.

What is the amount of the project with the highest monetary value?

Budget

5min
  -  
Hard 
  -  
NUM

Project Cost Management Project Management Public

A project you are managing had a starting budget of 180,000 USD and an expected duration of 1 year and 3 months. The work and budget are spread equally over the duration.

You are currently 8 months into the project, the work is on schedule, and so far you have spent 102,000 USD.

What is the cost variance of the project?

Use Free Questions On a Trial Plan

Premium Questions

The premium question library contains our unique, hand-crafted questions. We offer a refund if you find any of them answered online.

Questions
Next Task, Documentation, Mitigate Risk, Project Completion, Project Underway, Crash Sponsor, Exploit Risk, Insurance Value, Large Garden - Three Obstacles, Large Garden - Two Obstacles, Stakeholder Communications, Team Arguments, Plan Contribution, New Office
Skills
Project Planning Project Management Project Risk Management Project Cost Management Project Risk Management Gantt chart Team Communication
Score Distribution
# of candidates
0-33%
34-66%
67-100%
Score
Pricing For Premium Questions